4. Action on Monthly Facilities Matters: FMS Award of Construction Contracts, Professional Services Contracts and Emergency Contract Recommendation |
|
|
Strategic Plan Compatibility Statement:
|
Goal 3 Effective and Efficient Operations
|
|
|
Attachments:
|
Contracts requested for approval associated with construction and professional services are attached. |
|
|
File Attachment:
|
|
Background:
|
Recommended for the Board's approval at this meeting are: Construction Contracts Requested for Approval: - Newport Network Solutions for Proximity Card Access Control Installations at the following schools: Hampton Avenue, Lloyd Barbee Montessori, Milwaukee German Immersion, Thurston Woods, Townsend and Transition High School (Westside Academy II Building), Code: FAR 00 SPJ DW ECNC = $77,941.00 - Burkhart Construction Corporation for Interior Remodeling at Central Services, Code: FAR 00 RDP DW ECNC7 = $708,200.00 Professional Services Contracts for Approval: - MGT of America Consulting, LLC for Long-Range Facilities Master Planning Services for all MPS Sites, Code: FAR 00 RDP DW ECTS = $956,501.00 - Site Design Group, LTD for Playfield and Fieldhouse Design Services for Burnham Playfield and Alba School Playground at Walker Complex, Code: STS 00 RFI B2 ECNC and MBM 0A BDS A3 EMMB = $173,680.00 - Smith Group JJR for Playfield and Fieldhouse Design Services for Columbia Playfield, Custer Playfield, and Southlawn Playfield, Code: STS 00 RFI B2 ECNC = $272,400.00 Report of Emergency Contract: - Wilkin Insulation Company to address fireproofing material during the roof replacement project at Wisconsin Conservatory of Lifelong Learning, Code: FAR 00 MM2 WC ECNC HVA5 = $151,500.00 |
|
|
Fiscal Impact Statement:
|
This item authorizes expenditures: Construction Contracts: Total Construction Contracts Requested = $786,141.00 Professional Services Contracts: Total Professional Services Contracts Requested = $1,402,581.00 Report of Emergency Contract: Total of Emergency Contract = $151,500.00 |
|
|
Implementation and Assessment Plan: |
Upon approval by the Board, contracts will be implemented. |
|
|
Recommendation
|
Your Committee recommends that the Board authorize the attached construction contracts and professional services contracts described above. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Jacqueline M. Mann, Ph.D. - Board Clerk/Chief Officer |
|
|
|
|
|
|
|