Meeting Date:
|
|
Category:
|
|
Type:
|
|
Subject:
|
4. Action on Monthly Facilities Matters: FMS Award of Contracts and Equipment Purchase Recommendation |
|
|
Strategic Plan Compatibility Statement:
|
Goal 3 Effective and Efficient Operations
|
|
|
Attachments:
|
Contracts associated with construction are attached. |
|
|
File Attachment:
|
|
Background:
|
Recommended for the Board's approval at this meeting are: 1. Construction Contract: - Roman Electric Co., Inc. for Proximity Card Access Control Installations at Brown Street, Clarke Street, O. W. Holmes, Keefe Avenue, LaFollette School and Maryland Avenue, Code: FAR 00 SPJ DW ECNC = $81,250.00 - Allcon, LLC for Fire Alarm System Upgrade at Doerfler School, Code: FAR 00 MM2 DF ECNC = $144,395.00 2. Equipment Purchase: - Heat & Power Products to purchase the equipment for Cyclic Heating Plant Replacement at Hamilton High School, Code: FAR 00 MMS HA ECNC HVA4 = $339,255.00 |
|
|
Fiscal Impact Statement:
|
This item authorizes expenditures: 1. Construction Contract: Total Construction Contract Requested = $225,645.00 2. Equipment Purchase Total Cost of Equipment Purchase Requested = $339,255.00 |
|
|
Implementation and Assessment Plan: |
Upon approval by the Board, contracts will be implemented and equipment purchased. |
|
|
Recommendation
|
The Administration recommends that the Board authorize the attached construction contracts and equipment purchase described above. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Travis Luzney - Director |
|
Signed By: |
|
Wendell Willis - Director, MPS Foundation |
|
Signed By: |
|
Lynn Ruhl - Director of Financial Planning and Budget |
|
Signed By: |
|
Dr. Darienne Driver - Superintendent |
|
|
|
|
|
|
|